Wednesday, 16 September 2015

Working Schedule

2015/2016 Timetable
Subject to change once I've had my official timetable from Worcester University.

At university.
Not at university/work from home.

10/08      Type script.
17/08      Character designs.
24/08      Storyboard.
31/08      Animatic.

07/09      Set design.
14/09      Mock up set.
21/09      Create presentation.
               Finish mock up set.
28/09      First week of university.
   Polish pre-production work.
               Make materials list for sets and models.

05/10      Making models including replacement heads.
   Replacement heads to continue throughout semester one.
12/10      Making models.
19/10      Finishing models and starting pirate ship set.
26/10      Building Pirate ship set.
   Cast voice actors.

02/11      Set building.
09/11      Finishing set building.
               Voice recording?
16/11      Worcester week.
   Building props.
23/11      Test model movement.
               Voice recording?
30/11      Test models with replacement heads.
               Voice recording?

07/12      Make any improvements to models and set.     
14/12      Christmas break.
   Edit and layout voice recordings.
21/12      Christmas break.
   Practice animating with replacement heads.
28/12      Christmas break.
   Practice animating with replacement heads.

04/01      Back to university.
   Filming on pirate ship.
   Island set building.
11/01      Filming on pirate ship.
   Island set building.
18/01      Assessment week.
   Finish island set.
25/01      Worcester week.
   Finishing any props and improving pirate ship set.

01/02      Semester two.
   Filming on pirate ship.
08/02      Filming on pirate ship.
15/02      Filming on pirate ship.
22/02      Filming on island.
19/02      Filming on island.

07/03      Filming on island.
14/03      Filming on island.
21/03      Easter.
   Post-production of pirate ship animation.
28/03      Easter.
   Post-production of pirate ship animation.

04/04      Back to university.
   Additional filming on pirate ship set (if needed).
   Filming on island.
11/04      Post-production of island animation.
18/04      Post-production of island animation.
25/04      Post-production of pirate ship animation(if needed).
               Additional filming on island set (if needed).

02/05      Post-production of animation.
09/05     Assessment week.